India Extends Relief To Renewable Energy Projects Affected By COVID-19 Lockdown

Barely days after announcing that renewable energy project developers would be allowed to exercise force the majeure clause to seek extension of commissioning deadlines, India’s Ministry of New and Renewable Energy (MNRE) has expanded the scope of this relief.

Barely days after announcing that renewable energy project developers would be allowed to exercise force the majeure clause to seek extension of commissioning deadlines, India’s Ministry of New and Renewable Energy (MNRE) has expanded the scope of this relief.

Image: Zach Shahan — CleanTechnica.com

The MNRE has announced that commissioning deadlines of all renewable energy projects has been extended by 30 days beyond the period of lockdown related to COVID-19 outbreak. India announced a nation-wide lockdown between 24 March to 3 May 2020. Some states may extend the lockdown further.

While the government has allowed construction of power projects during lockdown, with this order commissioning deadlines will be extended by 30 days in addition to the number of lockdown days. The ministry further clarified that developers will not be required to submit any documentation to seek this extension, as was the case as per the previous order.

While the blanket extension of commissioning deadline will bring much-needed relief to developers, there are still demands for more flexible extensions. Some companies proposed an extension of up to 180 days citing delays in logistics and labor mobilization.

The MNRE has made an effort to minimize the strain on the renewable energy sector as a result of the COVID-19 outbreak. In an earlier order, the ministry had also clarified that must-run status enjoyed by renewable energy projects shall continue during the lockdown period and payments to renewable energy companies must not be delayed.

In February, we had covered a story about concerns over delays in commissioning of solar power projects in India due to its high dependency on Chinese modules. Now, Wood Mackenzie reports that around 3 gigawatts of solar and wind energy projects could be delayed in India this year. It has also reduced projected solar power capacity addition from 11.8 gigawatts to 8.9 gigawatts this year.

 
 
 
Appreciate CleanTechnica’s originality and cleantech news coverage? Consider becoming a CleanTechnica Member, Supporter, Technician, or Ambassador — or a patron on Patreon.
 

Don't want to miss a cleantech story? Sign up for daily news updates from CleanTechnica on email. Or follow us on Google News!
 

Have a tip for CleanTechnica, want to advertise, or want to suggest a guest for our CleanTech Talk podcast? Contact us here.
Advertisement
 
Written By

An avid follower of latest developments in the Indian renewable energy sector.

Comments

You May Also Like

Biofuels

At the coal face of a conference that involved governmental figures, academics, logistics customers and OEMs, the detailed technical conversations are almost all about...

Cars

After a very slow start, the Indian battery-electric car market is starting to get exciting. BYD is expanding its presence in the country, shifting...

Cars

India’s electric 2-wheeler market has been booming over the last few years. However, the electric car sector has been pretty slow. India’s electric car...

Clean Power

Indian hydropower company SJVN has announced start of construction of a large solar power park in the northern state of Rajasthan.  On January 3rd,...

Copyright © 2023 CleanTechnica. The content produced by this site is for entertainment purposes only. Opinions and comments published on this site may not be sanctioned by and do not necessarily represent the views of CleanTechnica, its owners, sponsors, affiliates, or subsidiaries.