Tesla has completed the world's largest battery grid storage system for Southern California Edison in just 94 days. It will replace a failed natural gas peaker plant and help make more renewable energy possible in the area.

Batteries

Tesla Needs Just 3 Months To Complete World’s Largest Grid Storage Facility

Tesla has completed the world’s largest battery grid storage system for Southern California Edison in just 94 days. It will replace a failed natural gas peaker plant and help make more renewable energy possible in the area.

Originally published on Solar Love.

Tesla has just completed the world’s largest battery grid storage facility and did it all in about three months from start to finish. The installation consists of 396 Tesla Powerpack units, each with 16,000 lithium ion battery cells, for a total of 210 kilowatt-hours of capacity in each Powerpack. In total, this one 20 megawatt/80 megawatt-hour installation is equivalent to 15% of all the installed grid storage presently available in the entire world.

Tesla Powerpack for grid storage

The project came about after Southern California Edison, which is the primary utility in southern California, experienced a major ecological disaster at a natural gas fired peaker plant located in Aliso Canyon near the Los Angeles neighborhood of Porter Ranch. It released thousands of tons of methane into the air before it was sealed last February, according to Bloomberg. Peaker plants are electrical generating stations that remain idle most of the day but are brought online to meet demands that exceed baseload capability, usually in the late afternoon and early evening.

“Batteries can…..meet peak demands with lower emissions than natural gas fired peakers by charging during low demand periods when excess wind and solar energy is being generated, and discharging during peak demand periods, which displaces the need to burn incremental natural gas in a peaker,” said Colin Cushnie, SCE vice president of energy procurement and management, in 2015. California is pressing all utility companies to add dramatically to the amount of renewable energy they produce and distribute.

The new facility is smaller, more flexible, and easier to expand than a peaker power plants. It also requires far less permitting than a normal peaker plant, especially in California which has adopted aggressive greenhouse gas emissions standards that are among the most rigorous in the nation. The speed with which the project was completed is almost as important as the cost. The facility can power 2,500 homes all day or 15,000 homes for four hours.

“There were teams working out there 24 hours a day, living in construction trailers and doing the commissioning work at two in the morning,” says Tesla’s chief technology officer, JB Straubel. “It feels like the kind of pace that we need to change the world. This project is exactly in line with our mission to accelerate sustainable technology and sustainable energy broadly for the world,” he added.

“The Mira Loma site can provide the equivalent energy storage of several hundred acres of solar panels,” Straubel said, adding that the facility “is able to to fit into this tight footprint right next to existing substations, and doesn’t really take up any substantial new land. And every piece of this product — the battery, the battery modules, the power electronics, the inverters — was assembled by Tesla workers right here in the US.” That is a huge feather in Tesla’s cap at a time when the putative president is pushing hard for more American jobs in the manufacturing sector.

Source: Teslarati

 
Appreciate CleanTechnica’s originality? Consider becoming a CleanTechnica Member, Supporter, Technician, or Ambassador — or a patron on Patreon.
 
 

Advertisement
 
Have a tip for CleanTechnica, want to advertise, or want to suggest a guest for our CleanTech Talk podcast? Contact us here.

Written By

Steve writes about the interface between technology and sustainability from his homes in Florida and Connecticut or anywhere else the Singularity may lead him. You can follow him on Twitter but not on any social media platforms run by evil overlords like Facebook.

Comments

You May Also Like

Batteries

In this episode of CleanTech Talk, RK Equity cofounder Howard Klein talked with me about what’s new in the EV battery market, current &...

Cars

This article is part of a short series on the history of EVs. You can find Part 1 here. The Tesla Roadster Both the...

Cars

It’s been clear to anyone who has been following the electric vehicle space for a while that the core matter for growth — whether...

Batteries

Tesla has been spending $2,984 on R&D per car sold. Its competitors? Not even half as much.

Copyright © 2021 CleanTechnica. The content produced by this site is for entertainment purposes only. Opinions and comments published on this site may not be sanctioned by and do not necessarily represent the views of CleanTechnica, its owners, sponsors, affiliates, or subsidiaries.