Danish Offshore Wind: It’s Getting Better All The Time

Sign up for daily news updates from CleanTechnica on email. Or follow us on Google News!

Originally published on Energy Post
by Mike Parr

Denmark continues to set the pace in driving down the cost of offshore wind. In its latest tender for 350 MW of near-shore wind farms the maximum price has again been reduced. Danish offshore wind now costs roughly half of what the new nuclear plant at Hinkley in the UK will cost.

Photo credit: Hornsrev.dkDenmark has launched a new tender round for 350MW of near-shore wind farms off the east coast of Jutland i.e. the Kattegat and its environs. This area has a number of features which favour low-cost offshore wind, for example relatively shallow waters, roughly 20 metres deep for 20km out from the coast, which in turn implies low-cost farm-to-shore power connections, plus a very favourable wind regime.

In the previous round of tenders for Horns Rev 3 (400MW), located off the west coast of Jutland in the North Sea, the bid price was €103/MWh. This was a considerable reduction on the price (€140/MWh) offered for Anholt (400MW in the Kattegat).

Levelised costs for these projects are difficult to estimate since once the ten years are finished the farm can only sell its power onto wholesale markets. I estimate that For Horns Rev 3 the LCOE (Levelised Cost of Electricity) based on a wholesale price of €35/MWh is likely to be around €74/MWh.

Lucky guess

In previous articles on this subject, I speculated that the next tender round could well be priced at around €93/MWh which would reduce LCOEs further.

As it turns out, this was either a) a lucky guess or b) the Danish energy regulator read the article and decided on a price of one € more at €94/MWh (actually 0.07 Danish Kroner/kWh – roughly €94/MWh at 7.45 Danish kroner per €). This is the maximum price for bids. This means that the final price offer could be lower. The price covers the first 50,000 full load hours from the farms, which depending on capacity factors will cover something in the range 8 to 11 years of wind farm operations. After that, farm revenue depends on the vagaries of the NordPool market. Another condition which sets it apart from other Contract for Differences (CfD) implemented in other countries (e.g. the UK) is that the €93 is not index linked (i.e. inflation-adjusted).

Other conditions worthy of note in this tender include the sale of 20% of the project to local residents at cost. The Danes (and Germans) take the idea of local ownership of generation seriously. The large number of energy co-ops in both countries bears witness to this. The regulator has included conditions, which will prevent financial engineering that could either dilute or weaken the participation of locals. For example, all shares will have the same ranking as others and there is no possibility of forced sale to other shareholders.

Chip in a few dollars a month to help support independent cleantech coverage that helps to accelerate the cleantech revolution!

Stark contrast

The tender also specifies that large wind turbines must be used in the range of 7 to 10 MW. Such turbines are likely to have higher capacity factors not least due to their height.

Taking a capacity factor of 60%, a discount rate of 5% and a wholesale rate of €35 gives a net present value (NPV) of €500m on a project with an investment of roughly €1000m (assuming a MW price of around €3m). The NPV represents total revenues minus costs over the entire period with a discount rate, i.e. the profit the project makes.

The internal rate of return (IRR) comes out at 12%. The above figures are over 28 years. Cost of a MWh over this period (and based on the above) is €68. Factors that could affect this include the capacity factor (a higher capacity factor will mean more energy and thus a lower overall price/MWh) and the wholesale price.

The above pricing and conditions sit in stark contrast to events in the UK and the proposed nuclear station at Hinkley. The table below summarises the main points.

 

Mike-Parr-Chart-01

It is clear is that the Danes have a firm grip on prices, costs and a determination to get maximum value for money for their citizens. By contrast, on the other side of the North Sea, in the UK, the current Tory government dishes out austerity for UK subjects and what could be characterized as large doses of charity for non-UK companies such as EDF. This in a country with the best resources for on and offshore wind, in Europe.

Proponents of the Hinkley project could argue that the current Danish tender is very small (at 350MW) compared to Hinkley (at 3200MW) and thus one is not comparing like-with-like. However, the Danes plan to install around 3000MW of offshore and near shore wind by 2020. Thus, whilst an individual project may be small, the overall programme is comparable in size/scale with Hinkley and other proposed nuclear stations.

Editor’s Note

Mike Parr is Director of energy consultancy PWR  which undertakes research in the area of climate change and renewables for clients which include a G7 country and global corporations. See here for his previous articles on Energy Post.

Note that compared to his previous article on the cost of offshore wind in Denmark, the author has re-assessed the wholesale price upwards from €25/MWh to €35, given that a new connection will be built between UK and Norway, which will impact NordPool prices. Hence there is a difference between the LCOE for Horns Rev 3 in this article and “lifetime” costs for Horns Rev in the previous article. The author has also made a more conservative assumption for the capacity factor of the Saeby wind farm, which he has adjusted from 65% to 60%.


Have a tip for CleanTechnica? Want to advertise? Want to suggest a guest for our CleanTech Talk podcast? Contact us here.

Latest CleanTechnica.TV Video


Advertisement
 
CleanTechnica uses affiliate links. See our policy here.

Guest Contributor

We publish a number of guest posts from experts in a large variety of fields. This is our contributor account for those special people, organizations, agencies, and companies.

Guest Contributor has 4389 posts and counting. See all posts by Guest Contributor